Nelson Point - OCRS Power Upgrade
Upgrade of power including installation of new cable ladder and new power circuits and outlets to existing DBs.
Key outcomes:
Installation of 100m of new cable ladder and cable ladder brackets
Installation of 30+ new single and 3 phase circuits plus outlets
Stage 1 and stage 2 testing of new installation
Rectification of existing circuit & labelling issues
Client:
BHP Rail
Project Dates:
01/12/2025 – 08/12/2025
Location:
Nelson Point, Port Hedland
Key Services:
Project Management, Execution - Mechanical, Execution - Electrical
Client Feedback:
“Just wanted to offer a big thank you to everyone that made this project a huge success. Extremely happy with Pirrpalas performance from start to finish. A team of professionals who took ownership from start to finish and executed a perfect installation, with the project handed back to operations within schedule. From project inception to hand back (89) days, a record we should all be very proud of."
– James Paterson, Specialist Project Management, BHP